Suggested Phasing

phase 1-2

 

phase 3-4

 

phase 5long

Target programme:

Each phase can be built in one season (April-October).The phases can be implemented in a parallel manner.

Funding is a critical factor in the timescale of the project. The physical construction can be completed in two or three seasons, with anticipated fundraising we believe the project would take five seasons to realise.

Phase one will consist of the school block in order to start providing education within a year of the project initiation.

Due to the site constraints, the majority of the site preparation work and the construction of the retaining walls will have to be included in phase one. This will be by far the largest phase.